Project Archive
City of Ventnor Sewer Main Replacement Project (Troy & Baton Rouge Avenues) Phase I
The Atlantic County Improvement Authority (ACIA) personnel would monitor the development of a design schedule and track the engineering firm’s progress through schematic and design development on to the construction documents phase of the project. With the approval of the City for design and construction documents, the Authority would assist the City with the public bidding of the project or would conduct its own bid cycle if that is the City’s desire. The end result would be a contract for construction between the civil construction contractor and the City of Ventnor or the ACIA.
The project management/contract administration staff will perform these duties: daily site inspections: maintain a daily activity log detailing work performed, project manning totals per trade and contractor, problems encountered, clarifications required, and schedule impacts; evaluate field conditions; coordinate design engineer inspections and site visits; review all payment applications for completeness and cross – reference with work in place to date prior to those applications being forwarded to the design engineer for possible certification; maintain a shop drawing/submittal log in order to expedite contractor submission and engineer review; evaluate change order requests relative to field events prior to their submission to the engineer for review and possible approval; coordination with all utilities involved with the project; facilitate utility communications with the design engineer to insure proper project coordination; facilitate the interface of contractors with utilities and governmental entities; conduct (chair) job progress meetings generating minutes of such; report to the City regarding project progress at regular intervals; facilitate the transmission of all close out, “punch list”, and “as built” information between the contractors and the design engineer
monitor the execution of “punchlist” requirements by all contractors.
The Demolition of Residential Building & Swimming Pool at 252 E. Jimmie Leeds Road, Galloway Township, NJ Block 981.01, Lot 16
The work required consists of furnishing all labor, equipment and materials necessary to perform demolition of the residential structure and in-ground swimming pool together with the removal and disposal of all materials as described in the technical specifications. All equipment, materials and any other work required for proper completion implied or intended in the Plans or Specifications, shall be furnished/installed without extra cost to the Owner. The work shall further included the removal and documented proper disposal of the asbestos containing building materials (ACBM) referenced in the ACER Associates, LLC summary report which is a component of the Project Manual.
Advertisement for Bids
Bid Package Pick up List
Bid Results List
Camp Acagisca ADA Retrofit
The ACIA is acting as the project
manager for the Camp Acagisca ADA Retrofit project. The
Architect for this project is Sykes O’Connor
Salerno Hazaveh Architects (SOSH). The project
consists of Renovations to the Lodge, Pavilion, Restrooms,
plumbing, mechanical, & electrical work. The site
previously was an old girl scout camp. With the help
of ACIA and the County Funds Camp Acagisca will be renovated
in summer, 2007.
Front End Documents and Drawings are available at
the ACIA for pick up and at a cost of $25.00. Addendums,
Bid Opening results, & List of Plan holders will be posted
on this website when available.
The Pre bid Meeting will be held at the ACIA’s Office, on Friday, June 15, 2007 at 2:00 pm SHARP!
The Bid Opening will be held at the ACIA’s Office, on Friday, June 29, 2007 at 2:00 pm SHARP
JFK Plaza Band Shell, Boardwalk, Atlantic
City (CLICK HERE for photos)
The ACIA is acting as the project manager for the erection of
a new 40' x 30' laminated wave beam band shell in JFK Plaza in
front of the Boardwalk Hall in Atlantic City. The structure
was purchased by the CRDA through the Atlantic City Special Improvement
District. It is being erected by Shore Building Contractors
Inc. of Hammonton, NJ via a contract bid and awarded by the ACIA
by means of CRDA funding.
Bid Opening Grid
Notice of Award
Bandshell Photos
Rehabilitation & Restoration of the
Fountain of Light
Brighton Park, Atlantic City, NJ
The Fountain of Light is a contributing historic element along
the Atlantic City Boardwalk as identified in the Preservation
Plan for the Atlantic City Boardwalk prepared by the CRDA and
dated September 2005. The Fountain of Light is likely eligible
for listing on the New Jersey and the National Registers of Historic
Places. The Fountain of Light was a gift from the General
Electric Company in 1929 on the 50th Anniversary of the founding
of Atlantic City. Restoration work now underway will return
the fountain to its original grandeur.
The ACIA is acting as the project manager for the restoration,
repair, and replacement of fountain elements including nozzles,
rings, and lights, paint removal and concrete patching of the exterior
lower basin walls and lower basin floor. The projects intention
is to restore the fountain to its original functional grandeur.
Bid Opening Grid
Notice of Award
Fountain of Light Photos
Atlantic County Criminal Court Complex
The
new Atlantic County Criminal Court Complex, located at 4997 Unami
Boulevard in Mays Landing, opened on May 3, 2004. The 176,000
square foot complex houses the offices of the county prosecutor
and sheriff in addition to the criminal court operations.
As project manager of the $40 million complex, the Improvement
Authority’s responsibilities included design and development,
contract administration, planning and permit approvals, road
construction, utility installation, and post-construction activities.
HUD Disaster Recovery Initiative
Atlantic County Three Bridges Project
The
ACIA was project manager and held the construction contract for
the reconstruction of Jeffers Landing Road in Egg Harbor Township,
two bridges in Egg Harbor City, and one bridge in Galloway Township.
The Office of Community Development secured $742,000 in funds
for the project from the U.S. Department of Housing and Urban
Development.
Boardwalk Hall
The
Authority continues to oversee the $90 million Renovation of
the Historic Boardwalk Hall. As part of the project, “The
New Atlantic Globe” or “The Mermaid and the Bathing
Beauty” by Kenneth Leap of Runnemede, New Jersey, was installed
in the entrance in the summer of 2004.
Organ Chambers Updated Information
Boardwalk Hall Photos
Richmond Avenue School Relocation
The Richmond Avenue School Relocation Project was the third
relocation project undertaken by the ACIA on behalf of the Atlantic
City Board of Education (ACBOE). This particular site consisted
of 26 separate properties, 21 of which were homeowners. The ACIA
successfully relocated 21 homeowners and five tenants from the
Richmond
Avenue site, which will enable the ACBOE to build a new Richmond
Avenue School. ACIA assisted two former tenants in becoming homeowners.
Façade Programs
Over the past eight years, the ACIA has acted as project manager
for various residential and commercial improvement programs in
Atlantic City. Pictured below is one of the properties that recently
received façade improvements as part of the Bungalow Park
Façade Program. The ACIA also completed the project management
of the Westside III and IV Phases of residential façade
improvements in 2004 in addition to beginning similar services
for the Ducktown and Boston/Sovereign Avenue Commercial Façade
Projects. Financing for these projects was provided by the Casino
Reinvestment Development Authority.
WESTSIDE FAÇADE PROGRAM – PHASE
V - ATLANTIC CITY, NJ
|